One drawing, one list. The venue layout, what it asks of a building, and every fixture and fitting, so anything can be added or taken out in one place.
The flagship venue, drawn to scale. One way through: in by the unmarked door, out through the shop.
The build decides the site. A building that cannot give these five things is not a candidate, whatever the rent.
At every viewing, three checks come first: Height. Tape it. If it is under 9.5 m, can the floor be dug? Power. Get the 300 kVA answer in writing. Licence. Is there a planning and licence route for late music?
The Three Models page checked line by line against the drawing, the build book and the room book.
The flagship fits on the 5 big numbers. 7 details do not fit yet, and 3 need checking. None of them is hard to fix, but the drawing and the books need to be brought into line before a designer or a landlord sees them.
| What | The Three Models page says | The drawing and the books say | Result |
|---|---|---|---|
| Shell | 49.8 × 30.3 m | 49.8 × 30.3 m | Fits |
| Floor area | 1,509 m² | 1,508.9 m² | Fits |
| Dome | 20.8 m across | 20.8 m across (radius 10.4 m) | Fits |
| Guests | 350, five shows a day | 350, five shows a day | Fits |
| Clear height | 9.5 m, or a dug floor | Dome crown 7.8 m inside a 9.5 m shell | FitsThe ring stage rises 1.2 m and sinks 1.2 m. The dig under the stage is now needed whatever the shell height. |
| Power | 300 kVA | 300 kVA (349 kW connected, 240 kW peak) | To checkThe load list was written before the ring stage lifts. The engineer should add them and confirm 300 kVA still holds. |
| The stage | A fixed listening pit, three steps | A ring stage in the dome: four rings, each moves up and down | Does not fit yetThe Three Models plan still shows the old pit. The drawing is newer. The page should show the ring stage. |
| The loop | Twelve stops, including "the pit" | Ten zones; the lounge has no pit drawn | Does not fit yetDecide: does the lounge keep its own small pit, or does the ring stage replace it? |
| Zone sizes | From the build book | Five zones are drawn smaller than the build book | Does not fit yetRecord store, gallery, lounge, back of house and the locks. The drawing is a sketch of what sits next to what; it needs redrawing to the book sizes. |
| Overlaps | Every room has its own space | The shop, the exit lock and both sound locks cut into the dome circle; the Halo sits inside the bar | Does not fit yetThe drawing places rooms next to each other without yet making them fit. An architect needs to lay it out properly. |
| Foyer | 9.0 × 8.4 m in the build book | Only the Halo ring is drawn | Does not fit yetThe foyer needs drawing as its own zone. |
| Back of house | 100.8 m² in the build book | 232 m² (2,500 sq ft) in the room book | Does not fit yetThe two books disagree. One number has to win. |
| Projectors | Eight, on the Worlds page and the build book | Fourteen in the room book | Does not fit yetThe two books disagree. The integrator quote settles it. |
| Models I and II | Drawn as plans on the page | No CAD drawing yet | To checkOnly the flagship has a drawing file. The 40-guest room and the 1,000 m² box are studies. |
| Build total | £8.77M, locked | £8.77M, locked | To checkThe total was set before the ring stage. The moving stage is not yet in it. |
Every item we know of, by area. Mark any item In, Out or To decide. Add what is missing. Then copy your changes and send them.
| Item | Detail | How many | Package | Status | Keep it? |
|---|
Your marks and additions are saved in this browser only. To make them part of the build, press “Copy my changes” and send them to the build desk. No costs are shown here. The only money figure is the locked build total of £8.77M, which was set before the ring stage, the record press, the artist’s counter and the people counters were added.
Checked against the data promise printed on every report: counted, not watched; named only by choice; the artist gets groups, never a person.
Counting people with ceiling sensors fits the promise. Taking payments fits. Marketing to a guest needs their yes. Joining all three into a record of one person breaks the promise unless that guest chose it.
| System | What it records | Who is identified | Result |
|---|---|---|---|
| Counting people (lidar)Ceiling sensors count how many people are in each room and how long they stay. | Shapes and positions. No faces, no pictures. | Nobody | Fits the promiseFits the promise, as long as a sensor track is never joined to a ticket or a phone. A notice at the door and a written privacy assessment are still needed. |
| ArrivalsThe ticket is scanned inside the door. | Which booking arrived, and when. | The ticket holder | Fits the promiseNeeded to run the night. Keep only what the booking needs. |
| Payments on siteBar, record store and shop are paid by card or by the app. | What was bought, where and when. Card numbers stay with the payment company. | The payer, when they pay by app or as a member | Only with the guest’s yesFine for receipts and accounts. Using it to learn about one person, or to market to them, needs their yes. |
| Marketing to guestsEmails and offers based on what a guest came to and bought. | A profile of one person. | The guest | Only with the guest’s yesOnly with a clear yes at sign-up, easy to withdraw. Never sold. The artist gets totals, never a person. |
| Following one guest through the houseJoining the sensor track, the ticket and the payments into one record of one person. | Everything one person did. | The guest | Breaks the promise as it standsThis breaks the promise "counted, not watched" unless that guest has chosen it as a member. It also raises the legal bar a great deal in the UK, the EU and Illinois. Do not build it without counsel. |
This is a design check, not legal advice. Before any of it is built: a written privacy assessment, a notice at the door, and counsel’s sign-off for each country we open in.